Project of the Month
„Adjustment of responsibilities and process organization
through the introduction of an in-house transport system“
CURRENT SITUATION
· Differing shift times (1 - 3 shifts)
· Different areas, each with their own responsibility:
· 2 areas carried out storage, retrieval, and transport activities
· 2 areas mechanically processed components
· The task was to develop a concept for the introduction and implementation of a
continuous internal transport system
IMPROVEMENT STEPS
Project Benchmarks
· Change of transport activities
from a 1-shift system to a 3-shift system without an increase in staff
· Increase in material availability and productivity
· Analyze the current situation and present it in a process diagram
· Develop a proposal for reorganization of the areas with responsibility according to the
following criteria:
· Value creation and logistics
· Consideration of the production process or production progress
· Summary of same activities
(e.g.: all transports between the areas from a single source)
· Train of staff with "Lean Manufacturing" simulation game
· Create clear separation of material cycles and storage locations - separation of
coated and uncoated parts
· Create clear company-wide applicable transport rules (who takes over
the transport and when?)
· Create a staffing plan to cover transports during operating hours,
without increasing staff
Separation of value adding processes and logistics
September
August
July
June
May
April
March
February